Sumter County will be performing micro paving on several roadways throughout The Villages beginning Thursday, July 19.

If your residence will be impacted, you will also receive a door knocker with additional information prior to the working beginning.  If you have any questions or would like additional information, contact Sumter County at (352) 689-4400. 

A tentative schedule can be found below: 

Day 1
Mundelein Place – Work will begin at Shorewood Street and stop before the cul-de-sac
Palantine Court – Work will begin at Shorewood Street and stop before the cul-de-sac
Elgin Street – Work will begin at Shorewood Street and stop before the cul-de-sac
Berkeley Lane – Work will begin at Shorewood Street and stop before the cul-de-sac
Shorewood Street – Work will begin at Talley Ridge and stop before the cul-de-sac
Wheeling Way – Work will begin at Talley Ridge and stop before the cul-de-sac
Deerfield Lane – Work will begin at Talley Ridge and stop before the cul-de-sac
Northbrook Place – Work will begin at Talley Ridge and stop before the cul-de-sac

Day 2
Niles Court – Work will begin at Talley Ridge and stop before the cul-de-sac
Addison Avenue – Work will begin at Talley Ridge and stop before the cul-de-sac
Weaton Court – Work will begin at Talley Ridge and stop before the cul-de-sac
Berwyn Way – Work will begin at Hillside Lane and stop before the cul-de-sac

Day 3
Hillside Lane – Work will begin at Oak Forrest and stop before the cul-de-sac
Maywood Court – Work will begin at Oak Forrest and stop before the cul-de-sac
Burbank Lane – Work will begin at Oak Forrest and stop before the cul-de-sac
Glenwood Place – Work will begin at Oak Forrest and stop before the cul-de-sac

Day 4
Highland Place – Work will begin at Riverdale Road and stop at Hobart Court
Lansing Way – Work will begin at Ramond and stop at Hobart Court
Ramon Road – Work will begin at Riverdale Road and stop at Hobart Court
Hobart Court – Work will begin at Oak Forrest and stop at Oak Forrest
Springfield Lane – Work will begin at Oak Forrest and stop at Oak Forrest
Riverdale Road – Work will begin at Oak Forrest and stop at Oak Forrest

Day 5 and 6
Oak Forrest Drive
Glenview Road – Work will begin at St. James Circle and stop at Buena Vista Boulevard

Neglect of golf course maintenance now costing us millions of dollars

In a Letter to the Editor, a Village of St. Charles resident argues that neglect of golf course maintenance is now costing residents millions of dollars.

Karen says her intent has been misinterpreted

A Village of Belle Aire resident who stirred quite a discussion with a previous Letter to the Editor, follows up to say that her intent was misinterpreted.

Our amenities are being used by families with kids

In a Letter to the Editor, a Village of Citrus Grove resident says she is not happy about families with kids using amenities paid for by residents.

Finally allocating funds to the golf courses!

A Village of Hadley resident said he is happy that more money is being allocated to the golf courses. Read his Letter to the Editor.

Trump is unfit for any office

A Village of Osceola Hills resident, in a Letter to the Editor, details why he thinks former President Trump is unfit to hold any office.